Undertake.

22 CCR 90060

Source text

11 segments

22 CCR 90060

22 CCR 90060

§ 90060. Undertake.

(a)

“Undertake” means any of the following:

(1)

Remodeling, installing, operating, continuing, acquiring, any combination of the aforementioned, or otherwise proceeding with a project or any part of a project.

(2)

The obligation of an expenditure, an expenditure, or commitment of funds for a project which shall include but not be limited to:

(A)

Construction of the project.

(B)

Equipment orders, purchases, leases or acquisition through other comparable arrangements or donation.

(C)

Provision of services through contract, lease or comparable arrangement.

(D)

Development of preliminary plans and outline specifications anticipated to cost more than the capital expenditure threshold.

(E)

Obtaining financing for a specified project where the financing is not contingent upon certificate of need or certificate of exemption approval.

(F)

Executing contracts for the project which are not contingent upon certificate of need or certificate of exemption approval.

(b)

The expenditure or commitment of funds to develop applications, studies, reports, schematics, long range planning or preliminary plans and outline specifications anticipated to cost not more than the capital expenditure threshold shall not be considered to be the undertaking of a project.